Crude Oil Transloading Facility

360 Rail Services staff have performed rail planning, surveying, rail infrastructure design, and
construction for the Casper Crude to Rail unloading facility in Casper, WY. 360’s staff was able to successfully work around a sensitive wetland environment in order to design and construct a track that allowed up to three unit trains to occupy the facility at one time. This project included the construction of manifest tracks, multiple loop tracks, a bad order track, and 5 at-grade crossings.

LOCATION
Casper, WY

PERIOD OF PERFORMANCE
April 2014 – December 2014

BNSF LEAD/MANIFEST TRACKS
22,000 Track Feet

LOOP TRACKS
15,700 Track Feet

BAD ORDER TRACKS
3,300 Track Feet

AT-GRADE CROSSINGS
5

TRACK FEET TOTAL
41,000 Track Feet