Crude Oil Unloading Facility

360 Rail Services staff have performed rail construction for the BNSF served Genesis Energy facility in New Orleans, LA. Here, 360 constructed a lead track, multiple loop tracks, a railcar repair track, and a bad order track. This facility allowed for multiple unit trains on site at one time. The project schedule for this facility was accelerated from 18 months to 8 months during construction. 360 Rail Service’s extensive experience in the construction of industrial projects was crucial for meeting the needs of the owner under these conditions.

LOCATION
Baton Rouge, LA

PERIOD OF PERFORMANCE
September 2015 – May 2016

EXXON LEAD TRACK
5,500 Track Feet

LOOP TRACKS
38,400 Track Feet

CAR REPAIR TRACKS
2,200 Track Feet

BAD ORDER TRACK
3,700 Track Feet

AT-GRADE CROSSINGS
15

TRACK FEET TOTAL
49,800 Track Feet