Oilseed Facility Loading /
Unloading Tracks

Overview 

 

LOCATION
Emporia, KS

SERVICES
Engineering, Construction

TRACK FEET TOTAL
41,000 Track Feet

PERIOD OF TRACK CONSTRUCTION
May 2019 - October 2019

360 Rail Services completed the design and construction of a 41,000-track foot rail spur for an oilseed processing facility in eastern Kansas. Our expert engineers took the design of this facility's track from an early stage and applied value engineering and extensive knowledge of rail operations to provide our client with a track that could be constructed at a great price. They operated with a very high degree of efficiency.

Maintenance job process
Rail checking process

This project was completed over 10 months. Our crews overcame unique environmental challenges with this project, such as the repeated flooding and freezing of the worksite during grading. Even with these challenges, the 360 Rail Services team delivered the highest quality track.

We Surpassed Expectations On These Railway Projects

The 360 Rail Services expert team delivers outstanding solutions and provides value to every project.

Crude Oil Unloading Facility
Crude Oil Unloading Facility

360 Rail Services' expert team helped to accelerate the construction schedule of this New Orelans facility from 18 months to 8 months.

Read More About the Project
Cheyenne Logistics Park
Cheyenne Logistics Park

360 Rail Services coordinated this project with state, municipal, military, and railway stakeholders.

Read More About the Project
Grain Transloading Facility
Grain Transloading Facility

Our experienced engineers and construction team overcame space limitations to create this facility capable of supporting an entire unit train in Alliance, NE.

Read More About the Project